Clifford Welch v Norfolk Southern Railway Company

Date Decided: May 27th, 2009
Originally Filed in: ()
Decided by: (State)
Court: U.S.D.C. Southern District of Illinois
Judge: Judge Murphy
Citation: 2009 WL 2365596

Background:
Plaintiff, Clifford Welch (Welch), brought this action against defendants, Norfolk Southern Railway Company (Norfolk) and Triple Crown Services Company (Triple Crown), seeking recovery for negligence pursuant to Federal Employers' Liability Act (FELA). The defendants have removed this case to federal Court in diversity jurisdiction. Norfolk and Triple Crown argued that Welch's FELA claim was fraudulent and thus not subject to the prohibition on removal of FELA actions. Welch has moved for remand of this action to state court on grounds that removal is untimely and section 1445(a) bars removal of his FELA claim.

Issues:
Is Norfolk's removal of Welch's FELA claim appropriate?

Held:
A defendant seeking to remove a case must file notice of removal within thirty days after service of the complaint in the case. If a case is not removable at the outset however, a notice of removal may be filed within 30 days after defendant receives "a copy of an amended pleading, motion, order or other paper from which it may first be ascertained that the case is one which is removable". Welch argued that because Norfolk and Triple Crown were served with his complaint February 12. 2009 and removal was not effected until March 17,2009 that the removal is untimely. The Defendants contended that even though Norfolk was serve, Triple Crown was never served because service was effected on a person not an authorized agent of Triple Crown for service of process. Furthermore, the Defendants argued that removal was timely because it was effected within thirty days of the date that they discovered Welch's FELA claim was fraudulent. This Court however, rejected the defendant's arguments. This Court relied on the "first-served" defendant" rule which holds a properly-served defendant's failure to effect timely removal of a case operates as a waiver of the right to remove that case with respect to all later-served defendants. This Court adopts the first-served rule rather than the last-served because it is consistent with the general principle that removal statutes are to be construed narrowly. Moreover, this Court rejected Norfolk and Triple Crown's argument on the ground of timely removal because they removed it within 30 days of discovering Welch's claim fraudulent because the defendants were doubtless aware of their asserted grounds for removal of this case. Accordingly this Court held that Norfolk and Triple Crown failed to timely remove this case and it is therefore denied.

Comments:
Failure to effect timely removal under §1446(b) is a procedural defect in removal, not jurisdictional one, and it is waived unless raised by a plaintiff within thirty days of removal. This requirement is mandatory and strictly applied. Welch has raised a timely objection to the procedural defect in the removal of this case and the Court remanded the case. Steve Gordon http://www.Gordon-Elias.com

<< PREVNEXT >>

Clifford Welch

Overall issues discussed or touched upon by this case:
Free Case Evaluation Form Talk to a Lawyer Now
Please complete the math to prove you are not a robot:
=
in-depth overview FELA click here

LATEST CASE LAWS

In re Ricky Joe Jones, Cheryl Ann Jones, Debtors

Date Decided: Jan 25th, 2011
Decided By: U.S. Court of Appeals, Tenth Circuit(Bankruptcy) (Federal) read more

Leandrew Lewis v. CSX Transportation, Inc.

Date Decided: Mar 10th, 2011
Decided By: Ohio Southern District Court (Federal) read more

Subscribe to Case Law Feed

LATEST RAILROAD NEWS

AMTRAK Train Kills Person on Railroad Tracks Near Sharon Massachusetts

 SHARON, Mass. – An Amtrak Acela train traveling from Washington D.C. to Boston struck and killed a person on the tracks on Monday, May 14, near Sharon, Mass. The accident occurred at about 4:45... read more

Railroad Workers Ratify New Contract with Great Western Railway of Colorado

 The Brotherhood of Locomotive Engineers and Trainmen (BLET), on behalf of 15 railroad workers, unanimously ratified a new three-year agreement with Great Western Railway of Colorado L.L.C. (GWR). GWR... read more

Seven Injured in Charlotte N.C. Accident After Car Collides with Light Rail Train

 CHARLOTTE, N.C. — Two vehicles and a light rail train were involved in an accident that sent seven people to local hospitals as a result of the accident. Four people were described as having... read more

BNSF Pays $29M in Largest Minnesota Wrongful Death Settlement

 ST. PAUL, Minn. — BNSF agreed to pay a $29M settlement to the families of four young people who tragically died in a train crash in Anoka on the night of Sept. 26, 2003. One of the victims, 23-year... read more

Subscribe RSS
Attorneys Refer your cases here

Toll-Free: 800-773-6770
Local: 713-668-9999
Fax: 713-668-1980
1811 Bering Drive, Suite 300
Houston, TX 77057

Of Counsel Offices

David Lockard
15 W Highland Ave
Philadelphia, PA 19118

Fred Bremseth
Minnesota Office
601 Carlson Parkway
Suite 995
Minnetonka, Minnesota 55305

Montana Office
100 North 27th Street
Suite 220
Billings, Montana 59101